This project is due to complete in November 2021 and is designed to provide cancer care closer to home. The new build includes the installation of two Linear accelerators and a CT scanner.

We worked closely with the client, main contractor and consultant team to protect the clients interests and monitor quality, conformance and design coordination during the construction phase.

A key issue was the coordination of our inspections with the Contractor to inspect and handover the new treatment areas where the Linear Accelerators and CT Scanner are located as part of a Sectional Completion to facilitate their installation.